PAPA KING’S NOTES: Reading What Is Written, Asking What Remains Unexplained
SAMARINDA, MJ — The recovery of excess payments for road, network, and irrigation projects under the East Kalimantan Public Works, Spatial Planning, and Housing and Settlement Areas Agency (PUPR-PERA) remains an open question. An audit of 17 project packages by the Audit Board of the Republic of Indonesia (BPK) identified deficiencies in work volumes that resulted in excess payments amounting to Rp3,835,145,471.07.
In BPK’s Audit Report (LHP) on the East Kalimantan Provincial Government’s 2025 Financial Statements, Report No. 16.B/T/LHP/DJPKN-VI.SMD/PPD.01/05/2026, dated May 21, 2026, contractors had returned only approximately Rp454.96 million. Consequently, Rp3,380,178,767.36 remained to be recovered and returned to the regional treasury.
BPK recommended that the excess payments be processed and recovered in accordance with applicable regulations. The finding relates to payments made for work volumes exceeding the physical quantities actually completed.
On July 28, 2026, the Acting Head of the East Kalimantan PUPR-PERA Agency, Irhamsyah, stated that some contractors had made repayments and provided proof of deposit, while others were still in the process of settling their obligations.
However, the publicly available information does not specify the latest repayment amount for these 17 project packages. It also remains unclear whether the entire outstanding Rp3.38 billion had been deposited into the regional treasury by November 2026.
The public is entitled to a transparent explanation, including the list of project packages, contractor names, repayment amounts for each project, and proof of deposits received by the regional government.
The question is straightforward: of the Rp3.38 billion that must be recovered, how much has actually been returned to the regional treasury?