PAPA KING’S NOTE’S — Reading What Is Written, Asking What Remains Unexplained
KUTAI KARTANEGARA, MJ — The Phase 2 Sebulu Bridge Construction Project in Kutai Kartanegara Regency was included in the audit conducted by the Audit Board of Indonesia on the Kutai Kartanegara Regency Government Financial Statements for Fiscal Year 2025. The audit document records a contract value of Rp136,350,270,000, with the service provider identified as LNN KSO.
According to Appendix B.13.1 of the BPK Audit Report, the contract bears number P.1036/DPU/BM/600.1.10.3/6/2025, dated June 26, 2025. The handover certificate (BAST) is recorded as having been issued on December 23, 2025.
BPK also identified an overpayment of Rp395,210,039.26. Of this amount, Rp135 million had been refunded, leaving an outstanding balance of Rp260,210,039.26, as recorded in the audit examination table.
Meanwhile, procurement data under tender code 10031502000 identifies PT Lestari Nauli Jaya as the winning bidder, with a bid of Rp136,350,270,096. The difference in the service provider’s name between the tender data and the audit appendix requires clarification through the contract documents and any joint operation (Kerja Sama Operasi/KSO) agreement.
The procurement history also shows a change in the budget ceiling. Two earlier tender processes listed a budget ceiling of Rp334,326,096,509, while the subsequent tender used a ceiling of Rp138,924,535,503. The initial process was recorded as canceled, and the following process as unsuccessful. The technical and administrative reasons behind the reduction in the budget ceiling still need to be confirmed with the relevant authorities.
Another entry in the Kutai Kartanegara Regency Government’s financial report states that the Phase II Sebulu Bridge construction project was reclassified under the Construction in Progress account, amounting to Rp139,552,531,720. This asset-accounting figure differs from the contract value and requires clarification based on the relevant technical documents and asset administration records.
MediaJakarta.co.id welcomes clarification from the Public Works Agency, the Commitment-Making Official (PPK), the Kutai Kartanegara Regency Procurement Unit (UKPBJ), and PT Lestari Nauli Jaya or the relevant KSO parties. The key questions concern the basis for the reduction in the budget ceiling, the identity of the business entity bound by the contract, and the follow-up on the outstanding overpayment recorded by BPK.
This report is based on audit documents and procurement data reviewed by the editorial team. Explanations from the relevant parties will be incorporated as part of the effort to provide complete and balanced information.